Northern Ireland Assembly Flax Flower Logo
Session 2009/2010
Fourth Report

Public Accounts Committee

Report on
Bringing The SS Nomadic to Belfast
– The Acquisition and Restoration of
The SS Nomadic

TOGETHER WITH THE MINUTES OF PROCEEDINGS OF THE COMMITTEE
RELATING TO THE REPORT AND THE MINUTES OF EVIDENCE

Ordered by The Public Accounts Committee to be printed 15 October 2009.
Report: 17/09/10R Public Accounts Committee

This document is available in a range of alternative formats.
For more information please contact the
Northern Ireland Assembly, Printed Paper Office,
Parliament Buildings, Stormont, Belfast, BT4 3XX
Tel: 028 9052 1078

Membership and Powers

The Public Accounts Committee is a Standing Committee established in accordance with Standing Orders under Section 60(3) of the Northern Ireland Act 1998. It is the statutory function of the Public Accounts Committee to consider the accounts and reports of the Comptroller and Auditor General laid before the Assembly.

The Public Accounts Committee is appointed under Assembly Standing Order No. 56 of the Standing Orders for the Northern Ireland Assembly. It has the power to send for persons, papers and records and to report from time to time. Neither the Chairperson nor Deputy Chairperson of the Committee shall be a member of the same political party as the Minister of Finance and Personnel or of any junior minister appointed to the Department of Finance and Personnel.

The Committee has 11 members including a Chairperson and Deputy Chairperson and a quorum of 5.

The membership of the Committee since 9 May 2007 has been as follows:

Mr Paul Maskey*** (Chairperson)
Mr Roy Beggs (Deputy Chairperson)

Mr Patsy McGlone ** Ms Dawn Purvis
Mr Jonathan Craig Mr David Hilditch ******
Mr John Dallat Mr Jim Shannon *****
Mr Trevor Lunn Mr Mitchel McLaughlin
Rt Hon Jeffrey Donaldson MP MLA *******

* Mr Mickey Brady replaced Mr Willie Clarke on 1 October 2007

* Mr Ian McCrea replaced Mr Mickey Brady on 21 January 2008

* Mr Jim Wells replaced Mr Ian McCrea on 26 May 2008

** Mr Patsy McGlone replaced Mr Thomas Burns on 4 March 2008

*** Mr Paul Maskey replaced Mr John O’Dowd on 20 May 2008

**** Mr George Robinson replaced Mr Simon Hamilton on 15 September 2008

***** Mr Jim Shannon replaced Mr David Hilditch on 15 September 2008

****** Mr David Hilditch replaced Mr George Robinson on 18 September 2009

******* Rt Hon Jeffrey Donaldson replaced Mr Jim Wells on 18 September 2009

Table of Contents

List of abbreviations used in the Report

Report

Introduction and Executive Summary

Summary of Recommendations

Departmental Oversight of the Trust

On Fundraising, Progressing the Project for the Centenary Celebrations and
Maximising Visitor Potential

Appendix 1:

Minutes of Proceedings

Appendix 2:

Minutes of Evidence

Appendix 3:

Correspondence

Appendix 4:

List of Witnesses

List of Abbreviations used in the Report

The Trust SS Nomadic Charitable Trust

DSD Department for Social Development

C&AG Comptroller and Auditor General

DFP Department of Finance and Personnel

Introduction and Executive Summary

1. The Public Accounts Committee (the Committee) met on 17 September 2009 to consider the Comptroller and Auditor General’s report on ‘Bringing the SS Nomadic to Belfast: The Acquisition and Restoration of the SS Nomadic’ (NIA 165/08-09). The witnesses were:

The Committee wrote to Mr Shannon on 22 September and 2 October 2009 with further queries, and he replied on 5 and 7 October 2009 (Appendix 3).

2. In January 2006 the Department for Social Development (the Department) purchased the SS Nomadic at auction. There were no other bidders. However, due to the risk of the vessel being withdrawn from sale and scrapped, the Department paid €1 over the auction reserve of £170,000 to secure it. The total cost of purchase, including auction fees and insurance, was £263,000.

3. Up to December 2008, the Department incurred a further £650,000 on the transportation and restoration of the vessel and providing financial assistance to the SS Nomadic Charitable Trust (the Trust). In addition, the cost to date of departmental staff time committed to the project is about £100,000; staff involvement from now until the initial stage of completion is likely to be of the same order and may increase as project oversight intensifies.

4. The Department actively encouraged the establishment of the Trust to take forward the restoration and ongoing maintenance of the vessel.

5. The Committee acknowledges that the Trust is a voluntary organisation staffed mainly by part-time workers and enthusiasts who were keen to see progress on the ship. It also notes that, in setting up the Trust, the Department sought to involve prominent local businessmen to give the project a business element.

6. To date the Trust has successfully lobbied to have the Nomadic included in the Core Collection of the National Historic Ships Register, a register of vessels considered to be of eminent importance in the UK. In the case of the Nomadic, its inclusion emphasises its importance as a White Star Line ship and its place in the UK’s industrial maritime heritage.

7. The Department currently estimates the cost of restoring the Nomadic to be in the range of £5 million to £7 million. A more accurate estimate will be provided on completion of a Conservation Management Plan currently being prepared for the Trust. Until this is finalised only essential restorative work will be undertaken.

8. In purchasing the Nomadic, the Department acknowledges that it was getting involved in areas in which it had very little experience. That is evident by the significant additional costs incurred by the Department since the Nomadic was purchased and the delays in finalising the Conservation Management Plan and raising the necessary funds for its restoration. The delays in progressing the project also increase the risk of reputational damage to both the Department and Trust should the Nomadic not be fully open to the public at the time of the centenary celebrations of the launch of the Titanic in 2011.

9. The Department’s business case for the Nomadic considered only the purchase and transportation of the vessel and did not adopt a longer term view by considering the implications of the restoration, including the impact on scarce public resources. This was one of the key lessons emerging from the saga of The Result which was purchased by the Ulster Folk and Transport Museum in 1970, but has never been fully restored. In considering that case, the Westminster Public Accounts Committee concluded that conducting an economic appraisal is not an option; it is always an essential part of good finance management and is vital to decision making and accountability.

10. While the Committee is hopeful that the Nomadic project will deliver value for money, in its view that remains to be seen. Completion of the Conservation Management Plan provides an opportunity to step back and re-assess the value for money of the project; preserving our heritage is important, but not at any cost.

11. Responsibility for the restoration of the Nomadic lies with the Trust. However, the Trust was specifically established at the Department’s request, and despite plans to transfer ownership of the Nomadic to the Trust, the vessel continues to be a departmental asset. In these circumstances the Committee considers that the Department cannot leave the Trust to its own devices. It should also ensure that the Trust complies with departmental policies and procedures and relevant domestic and EU legislation.

12. In its evidence the Department told the Committee that to safeguard the public purse it would not fund the costs of restoration — that was a matter for the Trust. The Committee notes however, that the majority of the funding secured to date by the Trust has been from public funds. In addition, the Committee is surprised that these funding awards were made before the final costs of the project have been determined.

13. In the Committee’s view the Department and Trust must continue to create and maintain effective relationships with those progressing the Titanic Quarter and the Titanic Signature Projects in order to maximise their impact on the Nomadic. The Department, in particular, must also be proactive in contributing to a wider overall maritime heritage strategy to ensure the Nomadic is given prominence within it.

14. In taking evidence, the Committee focused on two key areas. These were:

Summary of Recommendations

Departmental Oversight of the Trust

Recommendation 1

1. The Committee recommends that the Department should assess the arrangements currently in place between it and the Trust against best practice guidance and the recommendations contained in the Committee’s 2008 ‘Report on Good Governance - Effective Relationships between Departments and their Arm’s Length Bodies’, and adjust them accordingly.

Recommendation 2

2. The use of rolling contracts does not constitute best practice and is unlikely to deliver value for money. This point was previously made by the Westminster PAC in their report on ‘Governance Issues in the Department of Enterprise, Trade and Investment’s Former Local Enterprise Development Unit’. The Committee recommends that the Department of Finance and Personnel takes this opportunity to reiterate that point and draw departments’ attention to the formal guidance issued by the Central Procurement Directorate on the matter. Departments should also be reminded of the need to have proper systems in place to monitor and control contracts.

On fundraising, progressing the project for centenary celebrations and maximising visitor potential

Recommendation 3

3. Finalisation of the Conservation Management Plan is key to this project; it will determine what needs to be done and the likely cost of the work, and it will form the basis of any application the Trust may make to the Heritage Lottery Fund. However, its completion provides an opportunity to step back and re-assess the project. The Committee recommends that, on completion of the Plan, the Department should ask the Trust to revisit its economic appraisal and confirm to the Department’s satisfaction that the project will deliver value for money. The Committee agrees with the Westminster PAC’s conclusion on The Result that preserving our heritage is important, but not at any cost.

Recommendation 4

4. If the revised business case makes the case for taking the project forward, the Committee recommends that the Department and Trust must work together to ensure that contractors are appointed to enable work to commence at the earliest opportunity. It is critical to get the ship to a stage where it is open for viewing by the paying public who will then be contributing to its restoration costs and on-going maintenance, thus reducing the burden on the public purse.

Recommendation 5

5. The Committee recommends that the Department must be more proactive in working with the Trust to market the Nomadic and to link it in with other events, such as the Tall Ships. In addition, the Department and Trust must continue to create and maintain effective relationships with those progressing the Titanic Quarter and the Titanic Signature Projects in order to maximise their impact on the Nomadic. The Department, in particular, must also be proactive in contributing to a wider overall maritime heritage strategy to ensure the Nomadic is given prominence within it.

Departmental Oversight of the Trust

Governance arrangements

15. The Trust appointed consultants on a two-year contract to raise funds for the restoration of the Nomadic. Remuneration was set at £60,000 a year which was funded by a ring-fenced grant of £120,000 from the Department. The consultants’ contract provides for a one per cent bonus to be paid on achieving defined funding targets. The Department confirmed that none of the contracts for funding, from public bodies, awarded for the restoration of the SS Nomadic provide for commission payments as an eligible cost. In the Committee’s view it is important that none of these bonuses are paid from public funds. The Committee is also disappointed at the Department’s response that it “did not have a view" on the grounds that on the appropriateness of the targets or the potential bonus payments, the terms and conditions and the remuneration package of the consultant had been determined by the Trust.

16. Given that the Trust was established at the Department’s request, it is important that the governance arrangements comply with those set out in the Committee’s 2008 ‘Report on Good Governance — Effective Relationships between Departments and their Arm’s Length Bodies’.

Recommendation 1

The Committee recommends that the Department should assess the arrangements currently in place between it and the Trust against best practice guidance and the recommendations contained in the Committee’s 2008 ‘Report on Good Governance - Effective Relationships between Departments and their Arm’s Length Bodies’, and adjust them accordingly.

17. The Committee noted that, at the time of the Comptroller and Auditor General’s report (June 2009), the Department was unable to provide details of the cost of services provided by a firm of solicitors in July 2006 “because the invoices had not arrived". However, it also told the Committee that it monitored the contract expenditure on a monthly basis at divisional management meetings and the contractor’s performance was reviewed annually to decide whether there will be a fresh renewal of the contract. The Committee has difficulty reconciling these statements.

18. The Committee considers it unacceptable that it took three years for the Department to establish the cost of this work. It is also unacceptable to continually roll over contracts; they must be subject to periodic retendering.

Recommendation 2

The use of rolling contracts does not constitute best practice and is unlikely to deliver value for money. This point was previously made by the Westminster PAC in their report on ‘Governance Issues in the Department of Enterprise, Trade and Investment’s Former Local Enterprise Development Unit’. The Committee recommends that the Department of Finance and Personnel takes this opportunity to reiterate that point and draw the Department’s attention to the formal guidance issued by the Central Procurement Directorate on the matter. Departments should also be reminded of the need to have proper systems in place to monitor and control contracts.

Ownership of the Nomadic

19. The Department retains ownership of the Nomadic despite two specific conditions of DFP approval; (1) that the Department should transfer the ship as soon as possible and (2) that it should dispose of the ship if progress was not made in 18 months. The Department told the Committee that the latter condition was seen as a safeguard and it had decided to retain ownership of the ship until it was satisfied that a serious proposition was underway.

20. The Committee welcomes the Department’s intention to review the situation in spring 2010, by which stage the Department expects that the Trust will be in a more steady state, now that its funding is in a more secure position.

On Fundraising, Progressing the Project
for the Centenary Celebrations and
Maximising Visitor Potential

Completion of the Conservation Management Plan

21. The Committee is concerned that the Department did not take a long term view regarding the purchase of the Nomadic. The Department told the Committee that it had built in safeguards to protect the public purse, including that it would only fund the costs of bringing the Nomadic back to Belfast, with the costs of restoration “being a matter for the Trust and its fundraising activities". The Committee considers that this approach was naive. Major projects such as the restoration of the Nomadic undoubtedly benefit from the involvement of volunteers, enthusiasts and the business community. However, it is evident from the progress made to date that the Department needed to be more actively involved in providing direction and essential project management skills.

22. The Department is working to a “rough" figure of around £5 to £7 million for the cost of restoration. The lack of proper planning is clearly demonstrated in the significant variance between the estimated purchase and transport costs (£400,000) and actual expenditure on the Nomadic of over £900,000 by the end of December 2008; this excludes the cost of departmental staff time which is estimated to be in the region of £100, 000 to date.

23. The Committee noted that the original target date for finalising the full specification for the development and cost of restoring the Nomadic was March 2008. The Committee is concerned that a Conservation Management Plan will not now be completed until January 2010. At this stage the plan will still have to be considered by the Trust before the process of tendering and commissioning the restoration work begins. Only when the Trust receives completed tenders can the costs for restoration be finalised and a determination made of the extent of work that can be completed prior to 2011.

24. The Department estimates that evaluating the tenders and appointing the contractors will take “a couple of months" after the receipt of the Plan. The Committee is concerned that the Department and the Trust may be overly optimistic in their timetable. The Committee is also concerned about the process of repairing the ship and returning it to display order, which entails replacing the vessel’s superstructure (Stage 1), and partial internal fit-out of the vessel (Stage 2). Work will not commence, at the earliest, until April 2010, leaving less than one year for the restoration to have reached a stage where the Nomadic will be accessible to the public.

Recommendation 3

Finalisation of the Conservation Management Plan is key to this project; it will determine what needs to be done and the likely cost of the work, and will form the basis of any application the Trust may make to the Heritage Lottery Fund. However, its completion provides an opportunity to step back and re-assess the project. The Committee recommends that, on completion of the Plan, the Department should ask the Trust to revisit its economic appraisal and confirm to the Department’s satisfaction that the project will deliver value for money. The Committee agrees with the Westminster PAC’s conclusion on The Result that preserving our heritage is important, but not at any cost.

Recommendation 4

If the revised business case makes the case for taking the project forward, the Committee recommends that the Department and Trust must work together to ensure that contractors are appointed to enable work to commence at the earliest opportunity. It is critical to get the ship to a stage where it is open for viewing by the paying public who will then be contributing to its restoration costs and ongoing maintenance, thus reducing the burden on the public purse.

On fundraising

25. Although some £3.6 million has been raised towards the cost of restoration so far, over ninety per cent of this has come from public funds. The Committee notes the Department’s recognition that the challenge is now to “broaden [the funding base] further and to get as much commercial and private sector funding as possible". However, in the Committee’s opinion the original targets set for the fundraising consultants should have clearly identified the level of funding expected from the private sector.

The need for an effective marketing campaign

26. The Department acknowledged that the Nomadic is “a pretty unattractive prospect from the outside", and that the lack of visitor numbers during the Tall Ships event was, in part, due to its inaccessible location. However, in the Committee’s view the Tall Ships event provided an ideal opportunity to test public interest in the Nomadic and its ability to attract large footfalls. The Committee is surprised at the Department’s admission that extensive marketing was not carried out and only limited marketing associated it with the Tall Ships event. While the Committee notes that two or three successful meetings and performances took place on the ship and were reasonably well attended, overall it considers approximately 2,000 visitors out of a footfall of half a million to be a very disappointing result.

Recommendation 5

The Committee recommends that the Department must be more proactive, working with the Trust to market the Nomadic and to link it in with other events, such as the Tall Ships. In addition, the Department and Trust must continue to create and maintain effective relationships with those progressing the Titanic Quarter and the Titanic Signature Projects in order to maximise their impact on the Nomadic. The Department, in particular, must also be proactive in contributing to a wider overall maritime heritage strategy to ensure the Nomadic is given prominence within it.

Minutes of Proceedings
of the Committee
Relating to the Report

Thursday, 10 September 2009
Room 144, Parliament Buildings

Present: Mr Paul Maskey (Chairperson)
Mr Roy Beggs (Deputy Chairperson)
Mr Jonathan Craig
Mr John Dallat
Mr Trevor Lunn
Mr Patsy McGlone
Mr Mitchel McLaughlin
Ms Dawn Purvis
Mr Jim Shannon

In Attendance: Ms Aoibhinn Treanor (Assembly Clerk)
Mr Phil Pateman (Assistant Assembly Clerk)
Miss Danielle Best (Clerical Supervisor)
Mr Darren Weir (Clerical Officer)

Apologies: Mr George Robinson
Mr Jim Wells

The meeting opened at 2.02 pm in public session.

Additional Information regarding the NIAO report, ‘Bringing the SS Nomadic to Belfast’

Members noted the additional information regarding the subject of this report provided in the letters of 6 and 28 August 2009 from Alan Shannon, AO of the Department for Social Development (DSD).

3. Briefing on NIAO report ‘Bringing The SS Nomadic to Belfast – The Acquisition and Restoration of SS Nomadic’

Mr Kieran Donnelly, C&AG; Mr Brandon McMaster, Director; Vicki Quigley, Auditor; and Mr Joe Campbell, Audit Manager; briefed the Committee on the NIAO Report, ‘Bringing The SS Nomadic to Belfast – The Acquisition and Restoration of SS Nomadic’.

2.46 pm the meeting went into closed session.

The witnesses answered a number of questions put by members.

[EXTRACT]

Thursday, 17 September 2009
Room 144, Parliament Buildings

Present: Mr Paul Maskey (Chairperson)
Mr Roy Beggs (Deputy Chairperson)
Mr Jonathan Craig
Mr John Dallat
Mr David Hilditch
Rt Hon Jeffrey Donaldson MP MLA
Mr Patsy McGlone
Mr Mitchel McLaughlin
Ms Dawn Purvis
Mr Jim Shannon

In Attendance: Mr Paul Gill (Assembly Clerk)
Mr Phil Pateman (Assistant Assembly Clerk)
Miss Danielle Best (Clerical Supervisor)
Mr Darren Weir (Clerical Officer)

Apologies: Mr Trevor Lunn

The meeting opened at 2.03 pm in public session.

4. Evidence on NIAO report ‘Bringing The SS Nomadic to Belfast – The Acquisition and Restoration of SS Nomadic’

The Committee took oral evidence on the Northern Ireland Audit Office Report ‘Bringing the SS Nomadic to Belfast – The Acquisition and Restoration of the SS Nomadic’from:

Mr Alan Shannon, Permanent Secretary, Department of Social Development, and supporting official Mr Jackie Johnson.

The witnesses answered a number of questions put by the Committee.

Members requested that the witnesses should provide additional information to the Clerk on some issues raised as a result of the evidence session.

[EXTRACT]

Thursday, 24 September 2009
Room 144, Parliament Buildings

Present: Mr Paul Maskey (Chairperson)
Mr Roy Beggs (Deputy Chairperson)
Mr Jonathan Craig
Mr John Dallat
Rt Hon Jeffrey Donaldson MP MLA
Mr David Hilditch
Mr Trevor Lunn
Mr Patsy McGlone
Mr Mitchel McLaughlin
Ms Dawn Purvis
Mr Jim Shannon

In Attendance: Ms Aoibhinn Treanor (Assembly Clerk)
Mr Phil Pateman (Assistant Assembly Clerk)
Miss Danielle Best (Clerical Supervisor)
Mr Darren Weir (Clerical Officer)

The meeting opened at 2.11 pm in public session.

7. Issues Paper on evidence session ‘Bringing the SS Nomadic to Belfast – The Acquisition and Restoration of the SS Nomadic’.

Members considered an issues paper on this evidence session.

[EXTRACT]

Thursday, 15 October 2009
Room 144, Parliament Buildings

Present: Mr Paul Maskey (Chairperson)
Mr Roy Beggs (Deputy Chairperson)
Mr John Dallat
Rt Hon Jeffrey Donaldson MP MLA
Mr David Hilditch
Mr Trevor Lunn
Mr Patsy McGlone
Mr Mitchel McLaughlin
Mr Jim Shannon

In Attendance: Ms Aoibhinn Treanor (Assembly Clerk)
Mr Phil Pateman (Assistant Assembly Clerk)
Miss Danielle Best (Clerical Supervisor)
Mr Darren Weir (Clerical Officer)

Apologies: Mr Jonathan Craig
Ms Dawn Purvis

The meeting opened at 2.03 pm in public session.

8. Consideration of Draft Committee Report on Bringing the SS Nomadic to Belfast

Paragraphs 1 – 16 read and agreed

Recommendation 1 read and agreed.

Paragraphs 17 – 18 read and agreed.

Recommendation 2 read and agreed.

Paragraphs 19 – 24 read and agreed.

Recommendation 3 read and agreed.

Recommendation 4 read and agreed.

Paragraph 26 read, amended and agreed.

Recommendation 5 read and agreed.

Agreed: Members ordered the report to be printed.

Agreed: Members agreed that the report would be embargoed until 00.01 am on Thursday, 12 November 2009.

Agreed: Members agreed to launch the report with a press release to be agreed at a later meeting and to a Committee launch at a relevant venue.

[EXTRACT]

Appendix 2

Minutes of Evidence

17 September 2009

Members present for all or part of the proceedings:
Mr Paul Maskey (Chairperson)
Mr Roy Beggs (Deputy Chairperson)
Mr Jonathan Craig
Mr John Dallat
Mr Jeffrey Donaldson
Mr Patsy McGlone
Ms Dawn Purvis
Mr Jim Shannon

Witnesses:

Mr Jackie Johnson
Mr Alan Shannon

Department for Social Development

1. The Chairperson (Mr P Maskey): We now move on to the evidence session on the Audit Office report ‘Bringing the SS Nomadic to Belfast: The Acquisition and Restoration of the SS Nomadic’. Mr Shannon will respond to the report, supported by Mr Jackie Johnson, the director of the departmental team for Belfast city centre regeneration. You are both very welcome.

2. Figure 5 on page 24 of the report shows that the target for finalising the full specification for the development and cost of restoration of the Nomadic was March 2008. Paragraph 4.22 records that a conservation-management plan is currently being drawn up, and the work is expected to commence in December 2009. It is now September 2009, so has that plan been completed? What does it estimate the cost of the restoration to be?

3. Mr Alan Shannon (Department for Social Development): We do not yet know. Stage two of the conservation-management plan will set out what the actual plans will be, and those will then have to be costed by way of both estimates and tender. At the moment we are working to a rough figure of around £5 million.

4. Mr Jackie Johnson (Department for Social Development): It is £5 million to £7 million.

5. Mr A Shannon: We are hoping that it will be no more than that.

6. The Chairperson: The first part of the question was about the work that was expected to commence in December 2009. It is now September 2009 and there are no costs; you are still working to a rough figure of £5 million to £7 million. Do you think that that is good?

7. Mr A Shannon: We are not sure where that start date of December came from. The current plan is that stage two of the conservation-management plan will be available to the trust in January 2010. The trust will then meet to consider the proposals, and there will then be tendering and commissioning of work. We were not expecting work to begin in December.

8. Mr Johnson: There are two parts to the plan. The first part was completed in May and the second part will be completed in January. The restoration will begin if there are sufficient funds available to begin the work once the tendering is completed.

9. The Chairperson: You have estimated that the cost will be between £5 million and £7 million. When will that estimate be finalised and the work completed?

10. Mr Johnson: Once the tenders are returned. When the trust puts the work out to tender, it will then have definite costings available for the work to be completed up to 2011. Those will set out the budget for the first phase of the work. At the moment, the estimate is based on a full business case that was completed, which gathered market information for this type of restoration. The costs suggested by that business case will then be confirmed once the tenders are responded to.

11. The Chairperson: When will that be done?

12. Mr Johnson: Once the conservation-management plan is completed, the tenders will go out from January of next year.

13. The Chairperson: How long will the process then take after that?

14. Mr Johnson: It should take a couple of months to evaluate and to appoint the various contractors.

15. The Chairperson: Therefore, it has not been done yet. It has been planned for a long time yet it has not reached the stage when the work can be carried out. Do you think that that is good? The boat is there, yet the tendering process has not even begun and the costs have not been finalised after all this time.

16. Mr Johnson: The trust is a voluntary organisation staffed mainly by part-time workers who give up their time. I think that, in that context, it has made quite good progress. The trust set the targets itself, and those were quite challenging, as the Audit Office report indicates, but they were set largely by volunteers working part-time. The trust has only recently had the opportunity to employ a project manager, again on a part-time basis.

17. The Chairperson: OK. Appendix 2 to the report sets out the saga of the result, which has been the subject of no less than three reports by the Comptroller and Auditor General.

18. What lessons have you learned from the well-documented experience of the Result, and does it worry you that the Nomadic could end up the same way?

19. Mr A Shannon: That was certainly a worry. When we decided to purchase the Nomadic, which pre-dated the publication of a couple of those reports, we were aware that the Result was an issue. We were also aware of a previous attempt to purchase a ship — the Clyde Valley — and, therefore, of the very real risk of ending up with owning something that we purchased but with which we were making no progress.

20. Therefore, we tried to build in certain safeguards. Although the report states that the Department of Finance and Personnel introduced the condition that it would give 18 months for the people concerned to demonstrate that they could make progress on the Nomadic, it was actually the Minister of the day who introduced that condition. The condition was that, if at the end of 18 months, no satisfactory progress had been made, the ship would go back on the market, possibly even to the breakers’ yard. The thinking was that there would be no tolerance in having a ship lying around as an embarrassment for many years to come. That was the first safeguard.

21. The second safeguard, and this is where we drew on previous experience, was that we set up the charitable trust. In setting up that trust, we sought to engage a number of key people, including Belfast City Council and the Belfast Harbour Commissioners. We sought to involve some prominent local businessmen to give it a business element, and we also engaged some enthusiasts who were very keen to see progress on the ship.

22. We took a number of steps to safeguard the Nomadic itself so that it would be maintained and protected from deterioration. In taking those steps, we complied with the recommendations that the Audit Office report on the Result made.

23. The Chairperson: Paragraph 3.7 of the report states that although DFP approved a ceiling of £400,000 for the purchase and transportation of the vessel, the Department for Social Development had spent over £900,000 by the end of December 2008. Do you think that that demonstrates that your Department made a hasty decision at the outset and that it had no realistic idea of what the cost of purchasing and transporting the Nomadic back to Belfast would be? More importantly, did that demonstrate what the potential long-term implications for public expenditure might be?

24. Mr A Shannon: The decision was hasty in that it was made and executed within seven working days. That really was very unusual. It was hasty in that sense, but it was not reckless or ill-considered. We produced a business case, and we knew about the lessons that were learned from dealing with other ships of that kind.

25. We sought to protect the public purse by estimating as best we could the costs of purchasing and bringing back the ship. We did not get it quite right, but we got it nearly right. I think that we underestimated the cost of bringing the Nomadic into Belfast harbour and of carrying out some short-term maintenance work on it. The real safeguard for the public purse was the Minister’s announcement that he would fund the costs of bringing the Nomadic back but not the costs of restoration. That was to be a matter for the trust through its fundraising activities.

26. The Chairperson: I think that it is still hard to comprehend the estimated costs. I asked you a question earlier, and you stated that the estimated cost of restoration was between £5 million and £7 million. I am aware that that estimation was for the transport of the Nomadic back to Belfast; however, that figure was arrived at before that stage. I think that some aspects of that situation need to be dealt with.

27. Ms Purvis: Paragraph 2.19 of the report states that one of the conditions of DFP approval was that the ownership of the Nomadic would transfer to the charitable trust. Paragraph 2.21 records that your own solicitors consider that the trust should have an interest in the Nomadic to justify pursuing its charitable objectives. Why has the Department not complied with the conditions of the DFP approval and, according to what is written in the report, not taken the advice of its own solicitors?

28. Mr A Shannon: There were two DFP conditions. One was that we should transfer the ship to the trust as soon as possible; the other was that we should dispose of the ship if progress on it was not made in 18 months. We could not easily transfer the ship to another body and then take it back and dispose of it at a later stage. Therefore, we made the judgement — and the Minister was firmly of this view at the time — that we would retain control and ownership of the ship during that 18-month period until we were satisfied that a serious proposition was under way. At the end of the 18 months, we considered whether it would be appropriate to transfer ownership at that stage.

29. Ms Purvis: Can you clarify when the end of the 18-month period was?

30. Mr A Shannon: We took the view that the 18 months started when the trust was set up, which was in autumn 2006. Therefore, we were reviewing it in spring 2008. We talked to the trust at that stage. The trust felt that it was very much in fund-raising mode and was not on a secure financial footing or in a position from which it could guarantee carrying out a management function to our satisfaction. We agreed with that. We decided that we would retain ownership while things were going quite well and that we would review the situation in spring 2010, by which stage we expect that the trust will be in a more steady state, now that its funding is in a more secure position.

31. You touched on the lawyers’ advice. Now that the trust is in a position of managing substantial amounts of money, we feel that we need to have a stronger legal relationship with it, and we will be moving to establish that in the very near future.

32. Ms Purvis: Given that your Department is responsible for the charities legislation and that the solicitor advised the trust to have an interest in the project, what are the implications for the trust’s ability to raise funds?

33. Mr A Shannon: We have not found any problem so far in the trust raising funds under the current arrangement, but the stronger legal basis that I just mentioned would be aimed at removing any doubt about that. We will devise a legal instrument that will demonstrate that the trust has an interest in the ship.

34. Ms Purvis: Will that be while the Department retains ownership?

35. Mr A Shannon: While the Department retains ownership and until it reviews the situation next spring.

36. Mr Craig: You stated earlier that DFP said initially that the cost would be no more than £400,000; however, it turned out to be £900,000. You said that you almost got it right. I know that you had only seven days to produce a business plan. Can you clarify what you meant by that?

37. Mr A Shannon: The business plan covered the costs of purchase and transportation. That is where the figure of £400,000 came from. We actually purchased the ship for less than we had anticipated; we got it for €1 over the reserve price at the auction in Paris. We underestimated the transportation costs because the only information that we had about the state of the ship was a Harland and Wolff report that was done in 2004 that said that the Nomadic was seaworthy. However, when we got the ship to the sea and had a better look at it, we were advised that, until it had been taken out of the water and given a proper inspection, it would be too risky to tow it round the British Isles. Therefore, we had to rent a barge, and the cost of that was significantly more expensive than the cost of towing the ship. That was where the Department underestimated those costs.

38. As far as the £400,000 ceiling was concerned, DSD buying a ship was novel and contentious; therefore, the Department went to DFP for approval on the project. DFP agreed and approved both the purchase of the ship and the business case for its purchase. Once the ship arrived, it ceased to be novel and contentious, and the Department was spending money on the ship from its delegated authority. Both the Department and DFP are quite happy with that

39. Mr Craig: You can understand my concern when you suggested that the Department almost got it right. However, I thank you for clarifying that point. If I had done something like that at home, I know who I would have to answer to.

40. Mr A Shannon: As I said at the outset, DSD was getting involved in areas in which it had very little experience.

41. Ms Purvis: I want to follow on from that. You just said that the Department purchased the ship for €1 above the asking price, yet figure 2 on page 14 of the report does not show that to be the case.

42. Mr A Shannon: That was my recollection.

43. Ms Purvis: Are the amounts in figure 2 in question? Can you clarify that for me, please?

44. Mr Johnson: The purchase cost was based on the Department’s top limit, and its approval was based on not going over £204,000 at the auction for the ship. As Alan said, the actual amount that was paid was £171,000, which was €1 above the reserve price that the auctioneer placed on the SS Nomadic.

45. Ms Purvis: Therefore, the reserve that was placed on the ship was £170,000?

46. Mr A Shannon: Yes, or €300,000.

47. Ms Purvis: Yet the Department’s business case was for £204,000.

48. Mr Johnson: That was because the Department expected to have to bid at auction with other interested parties.

49. Ms Purvis: OK. I just wanted to clarify that.

50. Paragraphs 3.5 and 3.6 show that the Department spent £319,000 up to the end of December 2008. Has the Department incurred any further expenditure, and, if so, on what?

51. Mr Johnson: The Department has spent a further £29,000 on insurance for the year ahead, and it has also funded the trust with £9,000 for a Nomadic schools project. The purpose of that project is to raise schoolchildren’s awareness of the project, and 35 schools are taking part in it. There has also been some small, sundry expenditure, which brings the total for this year to £40,500.

52. Ms Purvis: £40,500?

53. Mr Johnson: Yes.

54. Ms Purvis: How much more do you anticipate spending on the project?

55. Mr A Shannon: That is hard to predict. The Department certainly sees itself supporting the trust, and the challenge for the Department in the future is enabling the trust to carry out the management function that the Department foresees for it. I am not sure whether we have a figure for that.

56. Mr Johnson: There is no figure at present for that. The Department is in discussions with the trust about what it will require for restoration management through to 2011. The trust will submit an application to the Department, which will be appraised, and a figure will then be agreed.

57. Ms Purvis: Will you provide the Committee with details on the total departmental staff time that has been spent on the project and its cost from inception to date? Will you also provide details on how much more time is likely to be spent on the project until it reaches fruition?

58. Mr Johnson: The Department will provide that information to the Committee in the next few days.

59. Ms Purvis: I appreciate that. Paragraph 3.18 of the report deals with fundraising, and it appears that even though the SS Nomadic is a public asset, most of the funding that has been raised has come from the public sector. Furthermore, the Department has employed a fund-raising consultant whose salary is paid from the public purse and who receives an extra 1% of his salary as commission. Is it appropriate that public sector funding is paying for the fund-raising consultant who is sourcing mostly public sector funding and receiving 1% commission mainly from public money?

60. Mr A Shannon: I will pass to Jackie Johnson for a detailed answer, but the important point is that the consultant was employed by the trust. The conditions of his employment were determined by the trust. The decision on the appropriate remuneration package was the judgement of the businessmen and others on the trust. Whether those bonuses are paid is a matter for the trust and subject to the conditions that were laid down, and I am not sure whether the Department has a view on that.

61. Mr Johnson: On a point of clarification, the Department is not funding any commission payments as part of its funding for that consultant. The Department is paying a grant of up to £120,000 over two years to employ the services of a fund-raising consultant; there is no provision in that grant for the trust to make commission payments.

62. Ms Purvis: Given that most of the funds that have been raised to this point are public money, will the commission that is paid to the consultant come out of that public money?

63. Mr Johnson: I do not think so. I have some background knowledge of the funding bodies, and I imagine that the conditions on those grants are such that they would not be paid for that purpose. However, we can check that and come back to the Committee with more information.

64. Ms Purvis: What proportions of funds that made up the original target were to be raised between public and private sector sources?

65. Mr Johnson: I understand that there is no proportional split. Those targets are numeric and relate to the total amount of funding that is to be raised after year one and year two. However, the sources of funds for the Nomadic-style restoration are not unusual, if one thinks of other national historic ships. For example, the restorations of the Cutty Sark, Mary Rose and SS Great Britain were largely dependent on public funds, whether they came from the lottery or elsewhere. Fund sourcing for the Nomadic is no different, but the challenge now is to broaden that further and to get as much commercial and private sector funding as possible.

66. Ms Purvis: Does the Department know the total amount of commercial or private sector funding that has been raised to date?

67. Mr Johnson: I have some figures. Two campaigns have raised modest amounts of public money. One campaign was sponsoring a rivet and the other was sponsoring a porthole. I believe that those campaigns raised more than £500. There has been a big contribution of just under £400,000 from the Titanic Quarter and the Harbour Commissioners to refurbish Hamilton Dock to provide a base for the refurbishment of the Nomadic. Those have been the two major contributions to the fund. Several thousand pounds has also been raised by the Institute of Directors, and Ulster Garden Villages is providing £200,000.

68. The Chairperson: You said £500; did you mean £500 or £500,000?

69. Ms Purvis: It was £500. How many rivets and portholes were sponsored?

70. Mr Johnson: Not a significant number.

71. Mr A Shannon: To be fair, there was a cheap shot at that fact in some media coverage the other day.

72. Ms Purvis: Yes.

73. Mr A Shannon: That sponsorship is the kind of little enterprise that works if a large number of people are visiting the ship. Last year, the ship was not open at all; this year, it was opened for the visit of the Tall Ships, which made the opportunities for that project very limited.

74. Ms Purvis: Figure 4 notes that the Department used a firm of solicitors to deal with the auction and the transportation of the Nomadic. It also gives a number of examples of services that DSD commissioned for the Nomadic. I note with some concern that the report records that the Department was unable to determine the cost of the service that that firm of solicitors provided. Are you able to provide that information to the Committee, including the value of the original contract with the firm?

75. Mr A Shannon: Yes. We could not determine the cost at the time, because the invoices had not arrived. I understand that the finalised cost is £25,814. We have had the contract in question for some years, and it has an annual value of about £300,000. We use the firm for a range of regeneration purposes, so the amount that we pay depends on the level of activity in any year.

76. Ms Purvis: How does your Department monitor that contract?

77. Mr Johnson: We monitor the expenditure on a monthly basis at our divisional management meetings. We also produce an annual performance report, which assesses the contractor’s performance. That is used to decide whether there will be a fresh approval for renewal of the contract.

78. Mr A Shannon: There is nothing dubious about the contract; it was tendered for and awarded. We use this particular company because the Government lawyers that are available to us have neither the time nor the expertise in development and property activities that we need.

79. Ms Purvis: Who from the Department attends the trust’s board meetings?

80. Mr A Shannon: Jackie attended those meetings at the start.

81. Mr Johnson: I attended at the start, and one of my senior management team, who is at grade 7, now attends.

82. Mr McGlone: The report states: “the Department was unable to provide us with evidence showing when each of the tenders was received, when the tenders were opened and who was present during the tender opening. To adopt these practices and retain evidence of them would accord with best practice and demonstrate openness and transparency."

83. Any of us who have been through a tendering process with other authorities and bodies will know that following those procedures is a given. Therefore, it is unusual that the Department did not adhere to that type of process and that those procedures were not followed, given that large amounts of money were involved. Why was that the case?

84. Mr Johnson: That refers to a specific tender for an economic appraisal that the trust tendered for. We provided the trust with grant aid for the procurement of the service, and it carried out the tender. We required the trust to adhere to Government tendering procedures, but it was the first time that a number of the trust’s staff had been involved in such an exercise. After they carried out their assessment, they did not retain the envelopes in which the tenders were delivered or the record sheet of who had been present when they were opened. All the other documentation was retained.

85. Mr McGlone: Are you saying that the Department had no connection with the trust staff during the tendering process?

86. Mr Johnson: The Department gave the trust staff instructions and reiterated the required practice later.

87. Mr McGlone: Did they not adhere to those instructions?

88. Mr Johnson: No, not on that occasion

89. Mr Dallat: It has been a long afternoon. I am trying to get my head around the project. Was it divine providence that the ship was named the Nomadic? I ask because it seems to have done nothing but wander about.

90. You mentioned the Cutty Sark, the Mary Rose and the Clyde Valley. In which category would you place the SS Nomadic? Please do not tell me that the SS Nomadic was gunrunning too; that would really scare me. At which end of the spectrum would you put that boat?

91. Mr A Shannon: I am no expert in that area, but —

92. Mr Dallat: Nor am I.

93. Mr A Shannon: However, I met the National Historic Ships committee on the day that it came to visit the SS Nomadic. The decision to register it fell to it. National Historic Ships has very demanding criteria; only a very small number of ships is on its register. I met the committee after its visit, and its members said that they were very impressed. They thought that it was a ship of significant historical interest, and in due course, they put it on their register. Where it is on the spectrum I could not say, other than to say that it has —

94. Mr Dallat: Please tell me that it is far away on the spectrum from the Clyde Valley, which I understand was towed out and scrapped.

95. Mr Johnson: I can clarify that for you. The UK National Historic Ships collection includes well over 1,000 vessels, but the core collection comprises a very small number — about 50 vessels. SS Nomadic is in that core collection, which emphasises its importance as a White Star Line ship and its place in the UK’s industrial maritime heritage. It is classed alongside the Cutty Sark, the SS Great Britain and the Mary Rose, and not on the outer fringes.

96. Mr Dallat: Perhaps some day there might be a whiskey named after it, the same as the Cutty Sark. Is that too optimistic?

97. You claimed in the business case at the time that the restoration of the SS Nomadic would enhance civic pride. Has it lived up to that?

98. Mr A Shannon: I suppose, like the French revolution, it is a little early to say. However, we have been pleased with the amount of public interest in the ship. In the first year that the ship was opened for viewing, we were pleasantly surprised by the number of people who came to see it. As something of interest, it is a pretty unattractive prospect from the outside, to be frank. It is interesting inside, but its exterior would not attract an audience at all.

99. Given the constraints, things are looking promising indeed. The ship will be part of a bigger picture, because we have the Titanic legacy, which many people feel is not being exploited fully from a tourism and civic pride perspective. Hopefully, when the signature project is built and the pump house and the drawing offices are opened, some other ships could become a part of a very interesting tourist attraction.

100. Mr Dallat: The report is depressing, but perhaps things have moved on a little since it was compiled. Is there now a greater prospect of the SS Nomadic fulfilling its potential? Will the trust, which did very little for a long time, be reinvigorated? What mechanisms are in place to ensure that a voluntary trust will work its tod off to achieve its aims and does not just absorb public money, rather than meet its targets for private donations?

101. Mr A Shannon: As you hinted already, we are involved fully ourselves. We have a member of staff who attends every meeting, and Jackie’s division monitors progress on a monthly basis. We were not too concerned by some of the delays, because we know that the business of getting people involved, and making applications for and receiving grants, can take a very long time. We now have promises of well over £3 million, which is well on the way to meeting the initial target of £5 million. I am very optimistic that the project will be successful and that we will meet the time targets.

102. Mr Dallat: You made a great deal of reference to sufficient progress being made before you will move to the next stage. Is that on an even keel now? Are we sure that sufficient progress has been made at each stage to deliver the project in its entirety?

103. Mr A Shannon: We believe so. Some of the missed targets that are quoted were not our targets; they were the trust’s targets. Those people give their time voluntarily. We have a high degree of confidence that the project will be delivered.

104. Mr Johnson: To be fair to the trust, it managed to secure the Hamilton dock as the base for the work. Moreover, it has been refurbished to allow work to begin on the Nomadic. That is a significant achievement. The fact that the trust managed to place the ship on the core collection of the National Historic Ships register is a huge bonus. Ships on that collection have benefited from Heritage Lottery funding over the years, and the conservation management plan will underpin the application to the Heritage Lottery Fund. The trust has taken a long-term view by ensuring that a good sum of money is in the pot before earnest restoration begins. It is taking every step along the way to ensure that that is delivered.

105. Mr Dallat: Finally, given that public money has been invested to regenerate that area of Belfast, and given that a great deal of investment still needs to take place before it begins to attract the desired number of visitors, is the Nomadic, by itself, a sufficient honeypot to achieve the increase in business that justifies the public investment?

106. Mr A Shannon: Not by itself, no: it must be part of a bigger enterprise. At least it is making a valuable contribution.

107. Mr Dallat: Are you confident that the other players are committed and are playing their part in painting the overall picture?

108. Mr A Shannon: We hope so. As you know, the Executive are dealing with a paper on the signature project, and the developer is proceeding with the Titanic Quarter. We are in discussions with others about the desirability of a maritime heritage strategy, into which the Nomadic would fit. Whether or not we receive UK heritage money will be a good test of whether it buys into that proposition. We are optimistic.

109. Mr Dallat: On that optimistic note, I will conclude.

110. Ms Purvis: You said earlier that the Minister at the time had given approval to purchase the ship but not to restore it; is that right?

111. Mr A Shannon: Public money would not pay for the actual capital —

112. Ms Purvis: Departmental money would not pay for the restoration?

113. Mr A Shannon: Yes, that is correct.

114. Ms Purvis: Given that the ship was listed as a departmental asset and that the risk was transferred to the trust to restore that asset, how confident are you that the restoration project will be completed in time for the centenary celebrations in 2012?

115. Mr A Shannon: Given that the trust has been promised more than the £3 million, we are confident that stage one of the restoration is pretty much guaranteed. Stage one will involve putting the superstructure back on again. I understand that stage two will involve fitting out the first part of the inside, and stage three will be further developments. We are optimistic that stage one will be achieved, and we are pretty hopeful that stage two will be well under way by the time of the centenary. The plan is that the ship will be open to the public at that point. The work might not be finished, but it will be open.

116. The Chairperson: You said that you paid €1 more than the asking price at the auction. How many other bidders were at the auction?

117. Mr A Shannon: We were the only bidder.

118. The Chairperson: You were the only bidder but you paid €1 more. I am trying to work out how that is value for money. You were the only bidder, yet you opened at higher than the asking price? I have seen programmes about auction houses, and people usually open with a bid well under the asking price and work their way up. Would that not have been a sensible approach?

119. Mr Johnson: It was made clear that, if it did not make its reserve price, the vessel would be withdrawn from the sale. The reserve price was, therefore, the guide. I will have to track down the records to confirm whether we opened the bidding at the reserve price. In order to get over the reserve price and acquire her, that was our final bid.

120. The Chairperson: The Committee would like more detail on that, because it is crucial to the report. I find it hard to believe that anyone would start bidding at the reserve price, never mind at €1 over that, regardless of the type of auction. The Committee’s remit is to scrutinise and to ensure that the Departments receive value for money. We hope that the project provides value for money, but that remains to be seen. Someone from your Department went to the auction, at which there were no other bidders. Given the absence of other bidders, would it not have been much more sensible to wait and subsequently try to enter into negotiations with the seller to determine whether the ship could have been purchased at a reduced price? It had been up for auction before and had not been sold. Could you not have stalled to ensure that you achieved the best deal?

121. Mr Johnson: The key point is that there had been two previous auctions. The authorities had made it clear that they wanted the ship removed from Le Havre harbour and that, if the reserve price were not met, it would simply be removed.

122. The Chairperson: Did any discussions take place with the seller before the auction or in the period between the two previous auctions?

123. Mr Johnson: My understanding is that the ship was an asset acquired by the court as part of someone’s estate. Therefore, no such negotiation was available to us.

124. The Chairperson: I still find it hard to understand, and, therefore, some additional information would be useful to the Committee. If, for example, the ship had not sold, negotiations could have taken place with the sellers. If they had been intending to scrap the ship, but you were prepared to pay them even €1 more than they would have received for doing so, that may have resulted in a better deal for taxpayers here.

125. Mr Beggs: My greater concern is about the process of repairing the ship and returning it to display order. You told the Committee that that is a staged process. It is critical to get the ship to a stage at which it is open for viewing by the paying public who will then be contributing. Until that stage is achieved, money is simply being poured in. How can we be confident that the process will reach that stage? Has the investment to date been prioritised to that end, or is any of the investment in, for example, the superstructure, going towards making the ship seaworthy? Presumably, the ship must be situated where it can be visited by the paying public who will contribute to the running costs.

126. Mr A Shannon: That is where the management plan comes in. When we see that plan in January, it will set out, as I understand it, the stages of the process to be followed. Once the trust has accepted that, our task will be to monitor its performance against that plan. The plan aims to have the ship ready for the public by April 2011.

127. The Chairperson: During the Tall Ships event, the public were able to view and go on board the Nomadic. Approximately 500,000 people visited the Tall Ships, and the event was a great success for the city. However, only 1,600 people visited the Nomadic. Given the number of people who were in the vicinity, is that a good result? I hope that the Nomadic is a success story of the future. Given the footfall in that area, is it good enough that only 1,600 people were sufficiently interested to visit the ship?

128. Mr A Shannon: We have just received a report on the event.

129. Mr Johnson: The Nomadic was not on the same site as the Tall Ships. It was a fair walk from that venue to the Hamilton dock. I surmise that the long walk put people off going to the dock to see it. Extensive marketing was not carried out; only limited marketing was done to associate it with the Tall Ships event. It was disappointing that more people did not turn out to see it. Two or three successful meetings and performances took place on the ship, and those were reasonably well attended.

130. Mr A Shannon: It was not as well marketed as it might have been. It did not make its way into the main Tall Ships advertising material, and it was pretty inaccessible. One had to go out of one’s way to get to it. I am not sure that that is a fair measure of its likely popularity.

131. Mr Beggs: Free bus transportation was put on around Belfast to manage the traffic attending the Tall Ships event. Could that have been co-ordinated to include the venue where the SS Nomadic was? Could the Department have contributed such ideas to try to help market the situation and generate the public’s interest in it, which is needed in order to retain it?

132. Mr A Shannon: My understanding is that it was only when it was established that the ship could be moved across the river from the other side and put in the Hamilton dock that it was certain that it could be opened. That only happened a few days before the Tall Ships event started. There was insufficient certainty about whether it could be opened to include it in the original material.

133. The Chairperson: I thank Jackie and Alan for answering our questions. I have no doubt that much work is to be done on the project, especially considering some of the questions that Dawn asked regarding the upcoming centenary of the sinking of the Titanic. The Nomadic Charitable Trust has much work to do, and we will probably put that in our report. We have sought further clarification from the Department, particularly on the issue to do with the auction.

Appendix 3

Correspondence

Correspondence of 6 August 2009
from Mr Alan Shannon

Correspondence of 6 August 2009

Correspondence of 28 August 2009
from Mr Alan Shannon

Correspondence of 28 August 2009

Correspondence of 15 September 2009
from L S Duncan

Correspondence of 15 September 2009

Chairperson’s Letter of 22 September 2009
to Mr Alan Shannon

NIA Logo

Public Accounts Committee

Mr Alan Shannon
Accounting Officer
Department for Social Development
Lighthouse Building
1 Cromac Place
Gasworks Business Park
Ormeau Road
Belfast BT7 2JB

Room 371
Parliament Buildings
BELFAST BT4 3XX

Tel: (028) 9052 1208
Fax: (028) 9052 0366
E: pac.committee@niassembly.gov.uk

22 September 2009

Dear Alan,

PAC evidence session on ‘Bringing the SS Nomadic to Belfast –
The Acquisition and Restoration of the SS Nomadic’

Thank you for your evidence to the Committee. As discussed at the meeting, the Committee wishes that you provide the following information to inform its deliberations:

1. The total time to date spent by, and cost of, departmental staff to the project since its inception; and the time and cost likely to be required for their involvement on the project from now until completion.

2. To clarify whether the fundraising consultant will be receiving commission payments of 1% on any funds raised from public money and what the individual numeric targets are for fundraising from the private and public sectors.

3. To clarify whether during the bidding process the Department opened at the reserve price.

4. To clarify whether any contact with the seller of the SS Nomadic was established prior to any of the auctions to try to acquire the vessel at a reduced cost.

I should appreciate your response by Monday 5 October 2009.

I am also copying this letter to David Thomson, Treasury Officer of Accounts, for his information.

Yours sincerely,

Paul Maskey signature

Paul Maskey

Chairperson
Public Accounts Committee

Chairperson’s Letter of 2 October 2009
to Mr Alan Shannon

NIA Logo

Public Accounts Committee

Mr Alan Shannon
Permanent Secretary
Department for Social Development

Room 371
Parliament Buildings
BELFAST BT4 3XX

Tel: (028) 9052 1208
Fax: (028) 9052 0366
E: pac.committee@niassembly.gov.uk

22 September 2009

Att: Letter from L S Duncan

Dear Alan,

PAC inquiry into Bringing the SS Nomadic to Belfast

The Committee has received correspondence, attached, calling into question the “pedigree" of the SS Nomadic.

For the avoidance of doubt in the public debate on the matter, the Committee would like you to detail the documentation now held by the Department which chart and authenticate the lineage of the SS Nomadic as a heritage asset.

I would be grateful for your reply by 7 October to facilitate its inclusion in the Committee’s report.

Yours sincerely,

Paul Maskey

Paul Maskey signature

Chairperson

Public Accounts Committee

Correspondence of 5 October 2009
from Mr Alan Shannon

From: The Permanent Secretary Lighthouse Building
Mr Alan Shannon 1 Cromac Place
Gasworks Business Park
Ormeau Road
BELFAST
BT7 2JB

Telephone: 028 90 829002
Facsimile: 028 90 829560
E-mail: perm.sec@dsdni.gov.uk

Mr Paul Maskey MLA
Chairperson
Public Accounts Committee
Room 371, Parliament Buildings
Stormont
BELFAST BT4 3XX 5th October 2009

Dear Paul

Thank you for your letter of the 22 September in which you asked for additional information to assist the Committee in preparing its report on ‘Bringing the Nomadic to Belfast – The Acquisition and Restoration of the SS Nomadic’.

The information that you requested is set out below:

1. The total time to date spent by, and cost of, departmental staff to the project since its inception; and the time and cost likely to be required for their involvement on the project from now until completion.

The total estimated time to date spent by Departmental staff working directly on the project since its inception is 605 working days at a cost of £99,157. The Department estimates that the level of staff involvement from now until the initial stage of completion is likely to be of the same order and may increase as project oversight intensifies during the restoration phase.

2. To clarify whether the fundraising consultant will be receiving commission payments of 1% on any funds raised from public money and what the individual numeric targets are for fundraising from the private and public sectors.

I can confirm that none of the contracts for funding, from public funding bodies, awarded for the restoration of the SS Nomadic provide for a 1% commission payment for the fundraising consultant as an eligible cost under the terms of the contracts. The Department understands that the numeric targets for the fundraising consultant set by the Trust are: £1million in Year One; and £5million by the end of Year Two of the contract. There are no separate targets for fundraising from the private and public sectors.

3. To clarify whether during the bidding process the Department opened at the reserve price.

The Department opened and concluded its bidding at the reserve price plus one Euro. The Department was advised by the French Court conducting the auction that this was required for the auction to proceed.

4. To clarify whether any contact with the seller of the SS Nomadic was established prior to any of the auctions to try to acquire the vessel at a reduced cost.

The Department’s only involvement was with the final auction at which it acquired the SS Nomadic. The vessel was auctioned in a French bankruptcy court, rather than a private auction house, as a property matter in connection with the previous owner’s estate and as such the Department did not have the opportunity to acquire the vessel by private treaty.

I hope this information is sufficient for your needs. If you require anything further please do not hesitate to contact me.

I have also copied this letter to David Thomson, Treasury Officer of Accounts, for his information.

Yours sincerely

Alan Shannon

Alan Shannon signature

Accounting Officer

Department for Social Development

cc David Thomson

Correspondence of 7 October 2009
from Mr Alan Shannon

From: The Permanent Secretary Lighthouse Building
Mr Alan Shannon 1 Cromac Place
Gasworks Business Park
Ormeau Road
BELFAST
BT7 2JB

Telephone: 028 90 829002
Facsimile: 028 90 829560
E-mail: perm.sec@dsdni.gov.uk

Mr Paul Maskey MLA
Chairperson
Public Accounts Committee
Room 371, Parliament Buildings
Stormont
BELFAST BT4 3XX 7th October 2009

Dear Paul

PAC Evidence Session on ‘Bringing The SS Nomadic to Belfast – The Acquisition and
Restoration of the SS Nomadic’

Thank you for letter of 2 October 2009 in which you have asked the Department to detail the documentation now held by the Department which chart and authenticate the lineage of the SS Nomadic as a heritage asset.

The UK national body charged with the responsibility to authenticate the lineage of UK national maritime vessels is National Historic Ships. This body, with its governing Advisory Committee, was established in 2006 as a non-departmental public body reporting to the Department of Culture, Media and Sport with a specific remit to advise the Secretary of State and other public bodies on ship preservation and funding priorities. The Department for Social Development relies upon this body to provide the authentication for the SS Nomadic.

National Historic Ships has inspected the SS Nomadic and placed the vessel on the UK National Historic Ships Register – Core Collection, Certificate No. 2053. A copy of the citation on the history of the vessel and the statement of her significance, taken from the National Historic Ships website are attached. This can be viewed at website www.nationalhistoricships.org.uk.

Yours sincerely

Alan Shannon signature

Alan Shannon

Appendix 4

List of Witnesses
Who Gave Oral Evidence
to the Committee

List of Witnesses Who Gave
Oral Evidence to the Committee

1. Mr Alan Shannon, Accounting Officer, Department for Social Development

2. Mr Jackie Johnson, Director of Belfast City Centre Regeneration Division, Department for Social Development

3. Mr Kieran Donnelly, Comptroller and Auditor General

4. Mr David Thomson, Treasury Officer of Accounts